Construction of a dwelling house with economic and social objects and underground parking on the Myloslavska street land plot in the Desnyanskiy district of Kyiv
Construction of a dwelling house with economic and social objects and underground parking on the Myloslavska street land plot in the Desnyanskiy district of KyivConstruction of a dwelling house with economic and social objects and underground parking on the Myloslavska street land plot in the Desnyanskiy district of Kyiv
04.11.2014-26.12.2014

Construction of a dwelling house with economic and social objects and underground parking on the Myloslavska street land plot in the Desnyanskiy district of Kyiv

Project data:

Project description

The project provides for the construction of a dwelling house with economic and social objects and underground parking on the Myloslavska street land plot in the Desnyanskiy district of Kyiv (with the allocation of a share of apartments who were affected by illegal activities of construction companies "Elita-Center").

Technical and economic indicators

Land area: 0.524 ha;

Number of floors: 16-24;

GBA: 22,439 m2;

Total number of apartments: 320;

Area of the apartments: 15,524 m2;

Commercial premises: 1,320 m2;

Apartments for the "Elita-center": 1,179 m2;

Underground parking with 23 lots: 995 m2;

Estimated construction cost: UAH 211,461,307.00.

Status

According to the results of the tender for attracting an investor in the construction of an apartment building with objects of economic and social purpose and underground parking (with the allocation of a share of apartments for victims of the activity of "Elita-Center" company) on the Myloslavska street land plot in the Desnyanskiy district of Kyiv, the winner determined - utility company for building construction "Zhitloinvestbud - UKB", the results were approved by the Resolution of the Kyiv City State Administration № 2640 of December 26, 2014. An investment contract with an investor has been concluded. The winner paid to the budget of Kyiv UAH 1,175,701.50 for the creation of social and engineering-transport infrastructure. Construction of 2 sections of residential buildings has been completed. Finishing works are in progress. The commissioning of the facility in Q4 2021.